Siesta Water Reclamation Facility Demolition

The Siesta Key Water Reclamation Facility on Oakmont Place should be demolished by October of 2020, County Manager for the project, John Saputo IV, told Siesta Key Association members at the September 5th meeting. Contracts should be awarded in March or April, with 2-1/2 months of intense demolition to start in June 2020. Removal of 18 to 20 inch slabs of concrete will generate significant noise. The new master pump station and a 2-million gallon tank to be used for emergency overflow will remain. The county will schedule a public meeting close to the start of the project. Property owners within 1/2 mile radius of 5200 Oakmont Place should receive invitations.