Siesta Road Resurfacing Concludes

February 17, 2025 —

No additional streets are scheduled for paving on Siesta Key. The paving crew is moving off the Key and will begin milling and paving streets in the Coral Cove community. For weekly updates to the project, see the Sarasota County Capital Projects One Week Look Ahead

February 7, 2025 —

The following streets are tentatively scheduled for construction activities during the week of February 10, 2025: Givens Street, Higel Avenue, and Oxford Drive.

January 31, 2025 —

The following streets are tentatively scheduled for the week of February 3, 2025: Cape Aqua Drive, Point of Rocks Road, Point of Rocks Circle, Crescent Street, Dee Place, Aqua Drive.

January 25, 2025 —

The following streets are tentatively scheduled for the week of January 27, 2025: Winding Way, Siesta Cove Drive, N. View Drive, S. View Drive, Siesta Court and Cape Aqua Dr.

January 17, 2025 —

The following streets are tentatively scheduled for the week of January 20, 2025: Birdsong Lane, Winding Way, Siesta Cove Drive, N. View Drive, S. View Drive, Siesta Court and Cape Aqua Dr.

January 12, 2025 —

Due to the impacts of Hurricanes Helene and Milton, the Siesta Key road resurfacing project was suspended until January 2025. Paving operations are scheduled to resume the week of January 13, 2025 on the following streets: Commonwealth Drive, Birdsong Lane, Dewy Place, Oakmont Place, Winding Way, Siesta Cove Drive, N. View Drive, S. View Drive, and Siesta Court.

The construction contract for resurfacing Siesta roads includes milling and paving of existing roadways, pavement striping, ADA ramp modifications, curb repairs, and roadway base repairs to various residential roads. Milling and paving operations began on August 7, 2024.

Motorists and pedestrians are advised to use caution while traveling past the construction zones or activities. Anticipated completion of this project is Summer of 2025.