SKA is actively working to follow the progress of the Benderson Development proposal to build a mixed-use development at the corner of Stickney Point Road and US-41.  Our goal is to ensure that the final development has the least possible impact on Siesta Key and its residents.  At the moment all proposals are preliminary, but SKA will keep our members informed as the process progresses to stages that are ready for public discussion.

Documents filed with Sarasota County

Below are links to the documents filed with the County by the developer along with the latest advisory on the project from the County Planner.

Projected timeline

Based on the announcement of the revised application, and presuming the application does not require further changes during the process, the following is our estimate of key dates:
  • Revised application filed: June 28, 2017
  • Estimated end of County Staff Completeness Review: July 28 - August 13, 2017
  • Estimated first public hearing (Planning Commission): September 28 - October 13, 2017
  • Estimated County Commission Public Hearing: November 13 - December 28, 2017
Please be aware that these are simply estimates based on the timelines provided in the announcement of the revised application.  All are subject to change if revisions to the plan are made.  The County will announce all Public Hearings and SKA will keep members informed of announcements as they occur.